Sunday, July 18, 2010

The Hookup


Last Friday I did a day-trip to Shangri-La for the well hookup. The evening before, Taylor Excavating was on site to dig the trench from the well to the cabin. Record Concrete had left a hole in the foundation for the water with 2 PVC pipes that extended 4 feet beyond the foundation walls. As Dan Taylor had done the foundation excavating, he knew right where to find them.


On Friday, I rolled in at about 8 am, and Green Mountain Well pulled in at about 10. While I continued the electrical work - completing the rear lighting circuit and beginning on the bathroom - they installed the pressure tank, ran the lines, and lowered the pump into the well. After I made the electrical connection (they can do a run directly to the fuse box, but aren't licensed to tie into the line I had already provided), we fired 'er up. Pump? Check. Pressure? 50 lbs - Check. Cold, fresh water? Check.

We're in business.


Dan Taylor was back by 2:30 to fill in the trench, and by 5 pm I was back on the road. For those of you keeping score, the well package rang up at $6545, and the excavating $440. Water ain't cheap, but we sure are happy to have it.

Sunday, July 4, 2010

On Optimistic Estimates

Well, the fix is in: The revised septic is going to cost me about $6,700. Certainly better that the 11k+/- we were facing with the mound system, but significantly above the $5k I budgeted (and the $3,500 I was secretly hoping for). The same day the estimate came in, I happened to learn that psychologists long ago identified a systematic bias in humans toward overly optimistic estimates - even when those humans have experience with the thing being estimated. I don't have experience with estimating septic systems, but it helps to know that it wouldn't have mattered if I had. *sigh*

My original hope for this year had been to finish the siding (which means also building the front porch), install the electrical, hook up the well so we had water on the property (even if it was only through a hose) and get the septic installed. Doing this would mean that we could stay overnight and the exterior of the property would look finished - at least to the extent that the grass and grading would be complete.

The well, however, was about 2,000 more than I expected, and the septic looks like it will be the same, so something is going to have to wait. Our options:
  • Scrounge about $700 to put the septic in and wait on the well and porch
  • Finish hooking up the well, complete the porch and siding, and tuck away the remaining $2,500 toward next year's work.
I was on my way to arranging for the septic, but the LSW has convinced me that we should finish the well. Her reasoning? If we go with the well, porch and siding, at least we can say that everything we began this year is finished, and we have the option of staying overnight on occasion. If we go with the septic, we have the biggest remaining item out of the way, but only the electrical will actually be done, and we still can't use the place.

As always, I've asked Dan Taylor of Taylor excavating to take care of the trench from the well to the cabin, and Green Mountain Well will complete the process by adding the pump, pressure tank, hookup, sanitizing of the system and water testing. These items are supposed to come in at about $3,000 in total, and rest assured I've included a cushion to compensate for the so-called 'optimism bias' this time.

Monday, June 21, 2010

The Quest for Water: Update

I just spoke with Green Mountain Well.

The good news: We have 20 gallons per minute.
The bad news: They found it at 300'.

Why bad? Because I had budgeted based upon about 200'. And I had assumed 20' feet of well casing. An extra 100' of depth and 80' of casing adds more than $2,000 to the total cost, putting my hopes of installing the septic this year in jeopardy.

The septic monitoring was also a mixed bag. We can move to an in-ground system (which is good), but the perk results dictate a system that is pretty big (which ain't so good). Still, the revised system should be a whole lot less expensive than the mound, so we'll see.

[7/18/10 Update: I got the preceding paragraph wrong. In speaking with the engineer, I understand that the perk actually isn't particularly bad. The system looks big because it is designed for a 3-bedroom home rather than our modest little shoebox. Could I reduce the size? Yes? Should I? Probably not. If I want to expand some day, things will be a whole lot easier and cheaper if I take the incremental cost during the initial install; if I decide to sell, the value will be much higher if the new owners can easily expand.]

My goal this year had been to get both the well and septic in so that:
A) The land that was cleared wouldn't completely regrow to engulf the cabin
B) The value of the property would be significantly enhanced on the off chance we were forced to sell for some reason.

Right now the budget is such that I can either wait on the well pump or wait on the septic system. To meet both goals, I should opt for the former. Though without the well pump, I've got no water for the fledgling grass, and - if the summer is dry - I could end up engulfed in weeds and trees again, resulting in extra expense next year. I suppose the next step is to get some hard estimates on the revised septic...

Sunday, June 20, 2010

The Quest for Water


The well was scheduled for 6/17 - 18, and so we checked into the Saxtons River Inn on 6/16 and were on-site by 7:30 AM the next day. Anticipation gave way to cautious optimism by 9 am, and by 10:30 I sent the LSW to the highway in search of a cell phone signal to find out what was up.

While she was away, I continued plugging away at the wiring, distracted by every vehicle I could hear (but not see) slowing to round the sharp curve at the bottom of our road. At 11:30 the LSW reported that the crew was about 1/2 mile away if we wanted to stop over and get a status.

So that was the racket we had been hearing in the distance all morning!

I worked all day, becoming more irritated with each passing hour, but - in fairness - a message had been left on our home answering machine the evening of 6/16 to let us know they would likely be a day late. We just didn't think to check it. At 5 PM we packed it in and drove the 1/2 mile to find that they were finished, packing up, and about to drop the well-drilling rig off at our place.
And so it was that drilling commenced on 6/18 at about 10 AM, while the LSW and I strung wire and The Boy sat in front of the back door watching the action around the well site. At 4 PM, they closed up shop, having hit ledge at 100', inserted the well casing to that point, and drilled another 20 feet looking for water. Ed stopped by in the middle of the day to check the crew's progress, and explained that the drilling starts using a water mixture that is heavy enough to prevent the hole from collapsing when they remove the drill. As water is continually flushed out of the hole, it is checked to determine if the drill has hit ledge. Once it has, the water keeps the hole open while steel well casing is inserted down to ledge level, and the drilling proceeds using air until water is struck. In our area, they are expecting water somewhere between 100 and 250'. The drilling is pretty slow while they are using water, but speeds up significantly after. This means they should know on Monday where we stand.

Best case: They hit water before 150'
Worst case: They don't hit water after 280' and we have to decide whether or not to spend $2,500 on 'hydrofracking'

At about $9 a foot for drilling, I've got my fingers crossed...

Sunday, June 13, 2010

Rain, rain, go away!


LSW here.

Here's our new checklist before leaving for Shangri-La:
_Do we have the keys?
_Did we pack sweatshirts?
_Did we check the weather forecast?

This weekend we had the keys, but neglected the other two items. We arrived to find it A) pouring rain and B) freezing cold. In addition, our lumber hadn't been delivered.

Hmmm.This looked like quite a dilemma. And of course, there's always the question of what do you do with a four-year-old in a dark, cold cabin for eight hours? It was looking bleak. However, things turned around pretty quickly. The Boy was quite content to sit in the car and pretend he was driving while The Vermonster showed me how to hook up wires to sockets. Oh yes I did! I used wire cutters and a screw driver! I hooked up some electric shizz. No need for you, DeVry University.

Around lunchtime, I headed out to get some sandwiches and to find a place where I could get cell reception to make some calls. First, I called the lumber company and was told the wood was being delivered within the hour. Second, I called my parents who said they *might* come up to see the digs. I hoped to catch them before they left to say, "Don't come! It's raining cats and dogs!" But when my dad answered, he said they were at the Vermont rest stop.

Let me divert just a moment to say that the Vermont Welcome Center is an attraction onto itself. When you pull into the parking lot, there's an open barn/gazebo type place where the library raises money by selling home baked goods and used books. The main building is a huge, new barn-like structure with displays from area stores, tourist sites, etc. There are tons of brochures and of course, bathrooms. If you ever go to Vermont, be sure to take a break there.

So I got some sandwiches at the Putney Co-Op and got back to the cabin just before my parents arrived. Our first lunch guests! We showed them around the place ("This will be a closet, this will be a bathroom") and then I decided to head down to Brattleboro with them while the Vermonster worked on the electrical.

All that rain was a blessing in disguise. He got the bulk of the wiring done, which probably wouldn't have happened had it been sunny.

The Saxton's River Inn was booked for the night (there was a local music festival going on), so we stayed in a cabin at the Brattleboro North KOA campground. Had it been a nice evening, we could've sat outside and had a fire and roasted marshmallows. Instead, The Boy got to watch the first half hour of Toy Story and then we went in search of pizza. We ended up in Bellows Falls at the Athens Pizza & Family Restaurant. It's the kind of place where you give your order at the counter and then bring it to your table. We ordered a large pepperoni pizza and two glasses of Cabernet. The wine was chilled, so that tells you a little something about the place. We were hesitant to eat there because we live in Connecticut, the epicenter of fantastic pizza. We've never had good pizza outside of Connecticut, and the rest of New England suffers from Crappy Pizza Syndrome. I have to say, though, that this pizza was actually really good in a junk food sort of way. Even The Boy ate an entire piece. We went back to the rental cabin where all three of us immediately hit the hay and slept until 8.

This morning we went back to the cabin and The Vermonster finished up the wiring while I painted some more siding. We stopped at the Top of the Hill BBQ we always go to and had lunch and now we are back. For three whole days. On Thursday, the well drilling begins!

Monday, June 7, 2010

The Other 60 Percent

I read somewhere that when you have a lockable shell, you're only about 40 done. That seems slightly pessimistic when I quickly tick off the remaining items, but clearly realistic when I sit down to write out what still needs to be done in detail. Add in the amount of time it actually takes to cross any given item off the list, and you begin to wonder if you'll ever actually be finished.

But "the journey of a thousand miles begins with a single step", and so each weekend I plod along, a bit overwhelmed but still enjoying the journey. Since the last post, there have been 3 trips to Shangri-La, two solo and one with LSW and The Boy in tow.

On the first trip I arrived with a punch list of items: Finish siding the south wall, build the bridge between the lofts, and put up the walls in the crawlspace. A solid day's work, I figured forgetting that a day is 24 hours at best, and only 8 hours realistically given the 6 hours of travel. In the end, the siding was all I accomplished, and even that I ran out of before the south wall was done.

No worries, though - we had planned an overnight the following weekend, and we had big plans to make bigger progress. We were up early and out on time for once, the wife actually stayed awake the whole trip and companionable banter sped the journey along. The Boy was in a good mood, the sun was shining and the mercury settled in the low 70s. Everything was absolutely perfect until we pulled up in front of the cabin and I turned off the car.

"Tell me you brought the keys," I said to the LSW.
"I thought you had them," she replied.
Son of a ...

Faced with a challenge from the universe to practice my zen actively, I calmly dropped the family at our beloved Saxtons River Inn, and spent the next 6 hours in a round-trip journey to retrieve the keys.

Here's the thing, though: Compelled to book a second night, we were pleased to be given the best room in the place "because we were regulars". Sitting that second night with a cold beer after a long day of work on our private front porch overlooking the main street, I had one of those moments where everything - and I mean everything - felt perfect and I knew life could not possibly be any better. So there was that, anyway.

And what did we get done? The deck framing is in place for the front porch, the rear gable is ready for the power hookup and both the general and oven circuits have been run. Less work than I thought we could accomplish, but what else is new?

This last weekend I was on the road by 5:30 am and hard at work by 8:45. I would have been there a little sooner, but I couldn't resist stopping at the Saxtons River Market for a bottled water and a hot donut. Those donuts will kill me one day, but what a way to go. The weather was deceptive: It was the kind of day where you felt slightly chilled while standing still, but were pouring rivers of sweat as soon as you lifted any tool. Really, really, really, humid. I didn't do too bad, though: The walls are up in the crawlspace and the bridge is finally built between the lofts. I rewarded myself with a hot roast beef and Cheddar from the Putney Co-op and listened to the dishy 'Mrs. Astor Regrets' on CD on the way home. The latter is a guilty pleasure, but then who doesn't like to hear about the self-destruction of the rich?

Unless of course, you're the rich in question. Then it just sucks.

In other news, Larry expects to get the meter socket on the house this week, and he'll be contacting me soon about running the power to the panel and hooking up the first couple of circuits. I understand that the revised septic plans are on their way to the State of VT as of last Friday, and even as I write I'm waiting for a callback from Green Mountain Well Drilling about moving my well date from the end of July to the end of June. All good stuff.

Saturday, March 13, 2010

Checking In - March Edition

The snow is melting, the mercury is rising, and I'm slowly recovering my enthusiasm to get back to work. Looking at everything to be done, however, is a little overwhelming: Well, Septic, Landscaping, Electrical, Plumbing, Flooring, Wallboard, Cabinetry, appliances, fittings and fixtures, the remainder of the siding, front porch, back porch, deck, etc., etc. Easy enough if you're either made of money or willing to take out a loan. I'm not and I'm not, respectively, so I'm being forced to to scale back last year's end-of-season dream of hiring a contractor to do the rest for me. So what to tackle next, and how?

Mulling this over for the last month, I've decided on three priorities for this year:

1) Finish last year's work. This includes completing the interior wall framing (furnace room, bathroom and closet), completing the loft catwalk and installing stairs, and finishing the exterior siding. All of this can be done for less than $1,000 as I have half the materials on hand.

2) Get power to the cabin. I've been in full research mode on wiring, and I've concluded that 80% of it is work I can do myself. I'll hire an electrician to inspect the work, wire the load panel, and hook up to CVPS. Including materials, about $1,500.

3) Drill a well. Once we have water available on the property, the prospect of staying there won't be so daunting, even if the 'real' plumbing isn't yet in place. I also want to know for a fact that I have water before I invest in septic. So what's involved?

There seem to be 3 well drillers in the area, and I drove up today to meet with the one who's name I've heard most frequently. 'Ed' from Green Mountain Well Drilling met me promptly at 11 am, confirmed that he could get to the well site with his drilling rig, and then settled onto a stack of wood in the cabin to fill me in on the process. My notes:

  • Most drillers will drill the well, line it from the surface to the bedrock, test the water, install the pump, run the water and power lines to the house, install the pressure tank, and tie into power and plumbing if needed. Excavating for the power and water lines can be done for an extra fee.
  • Ed has done a number of wells in the area, including the one across the street. He expects that the lining will need to be about 40', and that we should hit adequate water at about 250'.
  • The worst case scenario is that we miss the water entirely and find we've got 400 feet and nothing to show for it. If that happens, I can do 'hydrofracking' (breaking new fissures in the bedrock by injecting pressurized water). It's expensive at $2,200, but he guarantees we'll get water.
  • All said an done, the job will be somewhere between $3,500 and $10,000, although he expects my job will probably work out to about $5,000.
  • Shangri-La's heavy equipment prohibition means we can't do the work until May 15th, although Ed noted that the lack of snow means the roads will likely be passable by late April. The work should take about 2 days in total.
  • He also noted that we may find that my water is high in minerals - particularly magnesium. If so, we may need to add a filter to the system.
It was a nice conversation, ranging from the business at hand to solar energy, the state of American manufacturing, local agriculture, and cooking. It occurred to me that it was the first time I had had the opportunity to invite someone inside the cabin to talk, and so - even though it was a professional call - you could argue that we've had our first house guest.

"This place is way overbuilt," he said, looking around. "It ain't gonna fall down, that's for sure."

"That's the nice thing about building it yourself," I replied. "You can do it the way you want to."