Once again last week I traded 6 hours in the truck for 1 hour on site. Remember my previous post about assuming nothing? Well I realized after our last trip that I hadn't verified the width of the walls, the size of the cellar hatch opening, the distance from the slab to the beam, etc. So, tape measure in hand, I left the house at 6:30 AM.
At least it was a nice day for a drive - sunny and about 75 - and, being Saturday, relatively light traffic. I arrived on site to find that the Excavator had completed the back-filling, removed the last tree that would block the drilling rig's access to the well site, and cleared the short stretch of brush to the nearest CVPS pole.
God this guy did a nice job. He worked a miracle on my (formerly) sloped property, and left me with a rock retaining wall to support the driveway and a nice rock border on the up-slope side of the driveway that tied into the wall we cut the driveway through. The septic job is his next year if he wants it.
I was surprised to find that the electrician had already put up the board for the temporary power, but disappointed to see that CVPS hadn't yet hooked it up. In a call to CVPS yesterday, they said the weather has been lousy and they hoped to have it in place next week - not good as we're supposed to begin building the floor this weekend. That will add 2 day's rental of a generator to my costs - about $120.
Turned out that the measurements were different from my assumptions, but not enough to have been fatal. No fox sightings this time, but I was visited by a bright yellow bird with black wings that I've never seen in the 'burbs.
Next weekend begins 'Phase Two'. Our goal: Lay down the sills and get the floor framed in preparation for help from my sister's family a the end of June.
A middle-aged corporate everyman struggles to realize his dreams of a place in the country
Shangri La
Showing posts with label Land Preparation. Show all posts
Showing posts with label Land Preparation. Show all posts
Tuesday, June 9, 2009
Friday, May 8, 2009
Prelude to a Cabin
Spent most of last Saturday in the truck, making the 6 hour round-trip to Shangri-la for a final inspection of the site before the trenches are dug for the foundation. It was 'green up VT' day, and everywhere I looked families were picking up roadside garbage (precious little, compared to CT) and stuffing it into green bags. Those who weren't seemed to be fly-fishing in the West River. I love this place.
On site, the leaves were just emerging, as were the bugs. I stayed for about a half hour before the swarm reached critical mass and chased me back into the truck. The excavator did a pretty good job leveling the land; the only change I made was moving the foundation markers 10' to the east to get a clear line of sight from the gable end to the nearest CVPS pole without having to take down a 50' pine.
On site, the leaves were just emerging, as were the bugs. I stayed for about a half hour before the swarm reached critical mass and chased me back into the truck. The excavator did a pretty good job leveling the land; the only change I made was moving the foundation markers 10' to the east to get a clear line of sight from the gable end to the nearest CVPS pole without having to take down a 50' pine.
Monday, April 27, 2009
Concrete Plans

My excavator called me last night from Orlando to let me know that the site had been graded if I wanted to take a final look before the foundation trenches were dug. I was impressed that he’d take time out from his vacation update me – my experience with contractors being more on the give-them-a-deposit-pray-they-get-around-to-it-this-year end of the spectrum.
When I met with him and the concrete guy 2 Saturdays ago, it was agreed that the foundation could go in right after May 15th – the date they lift the mud season heavy load restriction on Shangri-La’s roads. (The town only has 2 paved roads – the only two that don’t dead-end – and even they have dirt sections.) The concrete work would take 3 days, and a week or two to cure after that, setting my start date in early June.
That Saturday was also the first time the project began to feel a little intimidating. Standing in the center of this denuded patch of forest I was struck that I would have to actually construct a building here – possibly by myself – before the first frost. It suddenly seemed a tall order.
A few random notes from the last two weeks:
The cabin plans have always called for a porch, and it occurred to me that the right time to pour the footings is while the foundation is being done. My plans call for 5 piers for the front porch, and 2 piers for the back; the excavator agreed to do the work on a per hour basis – at $45, expecting about a ½ day’s work. He also agreed to pick up the sonitubes and footing forms. The concrete guy expected to have enough concrete in the truck to pour them, so he thought the charge would be minimal if anything at all. I may not build the porches this year, but at least we’ll be ready for them.
I met with the CVPS guy on the same day, and we talked about plans for underground service to the house. Turns out that the $35/foot I quoted here was specifically for underground service. If I went overhead, the charge would be less, involving only wire, the weather head and the meter – no pole needed if the gable end of the house was less than 125’ from the pole. (I should just squeak by on that one.) This option does mean that I’ll need temporary power, however, which will be an $80 setup charge plus the cost of an electrician.
The excavator noted that he saved the stone from the wall so he could put it back in place once the width and location of the driveway had been finalized. This wasn’t something I expected, and one more reason why I’d recommend this guy to anyone. Not only was he less expensive than the others, but he seems to take a lot of pride in his work. And a hell of a nice guy.
The concrete guy had quoted me about 5,200 over the phone based upon a level site. He spent almost an hour brainstorming with the excavator on how they could carve a roughly level area out of the 15% slope we had to work with. In the end, he noted that the price could go up by a couple hundred dollars if the forms need to be stepped. This was still significantly cheaper than the next bid, so I’m not concerned.
With the land cleared, we’re now in clear view of the neighbors across the street. Not terrible, but I preferred the out-in-the-woods feeling. We’ll need to do some landscaping eventually the reclaim some of the privacy. On the other hand, the new sight lines should deter any vandalism, so I’ll have to think about this.
Financial tally: $1,000 to the excavator for the balance of the land clearing, and $1,000 deposit on the grading and excavating. Last week I got the formal proposal from the concrete guy, and cut another check for half of the foundation work - $2,600.
When I met with him and the concrete guy 2 Saturdays ago, it was agreed that the foundation could go in right after May 15th – the date they lift the mud season heavy load restriction on Shangri-La’s roads. (The town only has 2 paved roads – the only two that don’t dead-end – and even they have dirt sections.) The concrete work would take 3 days, and a week or two to cure after that, setting my start date in early June.
That Saturday was also the first time the project began to feel a little intimidating. Standing in the center of this denuded patch of forest I was struck that I would have to actually construct a building here – possibly by myself – before the first frost. It suddenly seemed a tall order.
A few random notes from the last two weeks:
The cabin plans have always called for a porch, and it occurred to me that the right time to pour the footings is while the foundation is being done. My plans call for 5 piers for the front porch, and 2 piers for the back; the excavator agreed to do the work on a per hour basis – at $45, expecting about a ½ day’s work. He also agreed to pick up the sonitubes and footing forms. The concrete guy expected to have enough concrete in the truck to pour them, so he thought the charge would be minimal if anything at all. I may not build the porches this year, but at least we’ll be ready for them.
I met with the CVPS guy on the same day, and we talked about plans for underground service to the house. Turns out that the $35/foot I quoted here was specifically for underground service. If I went overhead, the charge would be less, involving only wire, the weather head and the meter – no pole needed if the gable end of the house was less than 125’ from the pole. (I should just squeak by on that one.) This option does mean that I’ll need temporary power, however, which will be an $80 setup charge plus the cost of an electrician.
The excavator noted that he saved the stone from the wall so he could put it back in place once the width and location of the driveway had been finalized. This wasn’t something I expected, and one more reason why I’d recommend this guy to anyone. Not only was he less expensive than the others, but he seems to take a lot of pride in his work. And a hell of a nice guy.
The concrete guy had quoted me about 5,200 over the phone based upon a level site. He spent almost an hour brainstorming with the excavator on how they could carve a roughly level area out of the 15% slope we had to work with. In the end, he noted that the price could go up by a couple hundred dollars if the forms need to be stepped. This was still significantly cheaper than the next bid, so I’m not concerned.
With the land cleared, we’re now in clear view of the neighbors across the street. Not terrible, but I preferred the out-in-the-woods feeling. We’ll need to do some landscaping eventually the reclaim some of the privacy. On the other hand, the new sight lines should deter any vandalism, so I’ll have to think about this.
Financial tally: $1,000 to the excavator for the balance of the land clearing, and $1,000 deposit on the grading and excavating. Last week I got the formal proposal from the concrete guy, and cut another check for half of the foundation work - $2,600.
Thursday, April 23, 2009
Wow.
Almost a month ago I spent the day in what felt like the middle of woods peering through the trees trying to see the 4 markers that defined my modest, 16 x 28 cabin. To get to the site, I had to park at the meetinghouse, climb over the stone wall, and trudge through the brush.
What a difference a few weeks makes. Last Saturday I arrived at 9 am and was able to drive right onto the cabin site and walk unimpeded over a little less than a quarter of an acre of gently sloping moonscape. It was exciting and intimidating all at once; suddenly it really felt like the project was underway.
I'd like to give you a picture right here, but, unfortunately, I forgot the camera. Sorry.
Saturday, April 11, 2009
And We're Off!

The bids have been rolling in over the last 2 weeks. Here’s the score:
Land Clearing:
Way back in November, I got a land-clearing estimate of $3,500 to $5,000 per acre via phone, but didn’t actually meet anyone on-site until 2 Saturdays ago. Over the course of an afternoon, I met with 3 excavators and gained the following info:
- 3 of the 40 – 60’ pine trees near the foundation should be pulled down or I’ll risk obliterating The Dream during a wind or ice storm. A 30’ pine fallen over the well site since the last visit was all the evidence I needed.
- Most of the remaining trees were small (less than 8” in diameter, and would be pretty easy to clear.
- The land is sloped at 15-20 degrees, and it will have to be cut back significantly to ensure the water drains away from the foundation.
- The grading of the driveway will need to be continued to the well site so the drilling rig can get to it and level itself. The land can be returned to it’s original slope after drilling is done.
- One of the contractors lived in the neighborhood, and he suggested a small culvert to channel water under the driveway where is meets the road. “There’s a lot of run off on this road during a storm.”
- Another contractor noted that I might need a ‘cut approval’ from the down to join the driveway to the road. A quick check with the road commissioner confirmed that there was no such requirement in Shangri-La. This place is a libertarian paradise.
- If the stumps can be buried on the property, it will be cheaper. As soon as they leave the property, they become garbage and must be disposed ‘appropriately’ – which will cost.
- Final finishing of the driveway should wait until both the foundation and septic work is done, due to the size of the equipment that will be on the property. Until then , the drive can be surface with rough stone.
Estimates? Low of $2,000 from the neighbor, mid of $2,810, and high of $4,500 (from someone who obviously thinks that ‘from Connecticut’ means monied and stupid). All estimates included the crushed stone for the driveway.
The neighbor - who does excavating as a second business - got the job last Wednesday, and the land was cleared by Sunday. We’re heading back up next weekend to see the work and settle up.
Excavating:
I didn’t realize when I started this that excavating and foundation-pouring were separate activities, but apparently they are. The concrete guys I talked to all had excavators they work with. Consequently, I had no line item in the budget for excavating. Oops. The same guys bidding on the land clearing also bid on the excavating, and the scores were similar: $2,000 from the neighbor, a little more from the middle guy, and another $4,500 for the one who mistakes me for a [former] derivatives broker. All included trenches for the forms, preparation for the rat slab, installation of foundation drainage pipe, installation of pipe/conduit for power and septic (to 10’ beyond the foundation), and backfilling.
I’m planning on giving the job to the neighbor, but I’ll wait until I see his land clearing work next weekend.
Foundation:
The foundation is going to be a simple 16’ x 28’ crawlspace with a “rat slab”. The footings will be laid at 4’ below grade (to prevent frost-heave), and will be topped with 8” wide walls. There will be two vents and a 4’ access opening. All concrete will be rated at 3,000 lbs, and the work will take 3 days.
In this case, the low bid also came from my neighbor: $2,200. This from a contact of his in the neighboring town who does concrete work ‘on the side’. This sounded good until the next two estimates came in: $5,160 and $5,800. Some further research revealed the concrete cost alone to be about 2,100, never mind the rebar, bolts, oil for the forms, labor, and rat slab mesh. Suddenly the low guy was suspect, and I reverted to a piece of advice I’ve heard over and over again: Be cautious of the lowest and highest bids. Today I confirmed with the $5,160 guy, who also agreed to throw in the concrete for 7 frost-line piers for a deck, given that there will probably be more on the truck than he’ll actually need.
Total anticipated bill for land clearing and foundation: $9,160 – about $4,000 more than I budgeted for. Say it with me: Twice as expensive as you expected, and three times as long.
Monday, March 30, 2009
Spring Fever
Lured by the Saxtons River Inn's 2-for-1 offer through March 31, we packed up the car and headed for Shangri-La this last weekend. Me, the LSW and The Boy were joined by The Niece (who has been crashing at our place over the last year while attending a local college) and the LSW's sister, who was looking for an excuse to spend a few days exploring a new place and sleeping late. My goal was to meet with 3 excavating and concrete contractors to get the ball rolling on The Dream.
But first things first: The food.
Dinner at the Saxtons River Inn is still outstanding - especially the crispy onion rings, fish and fries. The LSW and her sister were united on the virtues of the pulled pork and the burger, respectively, but The Niece apparently prefers soggy french fries to crispy ones, so she was less enthused.
Unfortunately, the Inn falls short in the breakfast category - providing only coffee, apple juice, store danish, apples and oranges. Luckily, The Golden Egg is only a block away and offers the second-best breakfast in New England (the first being King's in Newtown, CT). I recommend the Vermonter Skillet if you're going, or perhaps the blueberry crepes. The breakfast sandwich was also good, but the fact that they don't offer it with Vermont cheddar is almost unforgivable.
On Saturday evening, we descended upon the Putney Diner to sample their pies on the recommendation of Mr and Mrs Chops. In the spirit of adventure, I ordered a Reuben for the first time in my life. Good choice, that; I've got a new favorite sandwich. The cole slaw was fresh and the pickles agreeably sour, but the fries were soggy, to my dismay and The Niece's delight. The 4 of us split 3 slices of pie at the end of the meal - Apple, Chocolate Cream and Maple Walnut. The verdict: The apple wasn't as good as the LSW's, but the Maple Walnut and Chocolate Cream were worth the trip.
The LSW will be reporting on the handmade chocolates she tracked down in Walpole, NH here. Ye gods, they are good! And then there was 'Smokin' Bowls' on 123 between Bellows Falls and Chester:

Does this look good or what? We ordered the 'Brownie of the day'; tasty but - unfortunately - strictly legal.
Now, down to business:
As I noted, the reason for the trip was to get land clearing, excavating, and foundation estimates. To that end, I spent all of Friday afternoon and part of Saturday morning on site, taking time to walk the property and clearing some of the underbrush between appointments. The weather was in the mid-50's and the sun shining, and I spent most of the day in a T-shirt. Nice.
I started by locating the engineer's markers, which was a little challenging as a fallen pine took out the well marker. Once I found it, I was able to triangulate the planned position of the cabin and mark it with orange poles. The slope of the land seemed to lend itself to a walk-out basement, and before I knew it I was getting estimates on one at 28 x 32 in addition to my less ambitious 16 x 28 crawl space.
I talked with 6 contractors in total. Some things I learned:
The 'official' estimates are all expected before the end of this week, so I anticipate we'll be underway within a month. The first step will be land clearing, which is expected to take about 2-days, as most of the trees on the site are relatively small.
Here's a shot of the building site:

The view behind the future cabin:

In this shot the two large boulders mark the future driveway:

Incidentally, the major lesson learned on this trip was that a Hyundai Sonata is not the best vehicle with which to sample dirt-surfaced mountain passes during mud season. I see a Subaru in the LSW's future...
But first things first: The food.
Dinner at the Saxtons River Inn is still outstanding - especially the crispy onion rings, fish and fries. The LSW and her sister were united on the virtues of the pulled pork and the burger, respectively, but The Niece apparently prefers soggy french fries to crispy ones, so she was less enthused.
Unfortunately, the Inn falls short in the breakfast category - providing only coffee, apple juice, store danish, apples and oranges. Luckily, The Golden Egg is only a block away and offers the second-best breakfast in New England (the first being King's in Newtown, CT). I recommend the Vermonter Skillet if you're going, or perhaps the blueberry crepes. The breakfast sandwich was also good, but the fact that they don't offer it with Vermont cheddar is almost unforgivable.
On Saturday evening, we descended upon the Putney Diner to sample their pies on the recommendation of Mr and Mrs Chops. In the spirit of adventure, I ordered a Reuben for the first time in my life. Good choice, that; I've got a new favorite sandwich. The cole slaw was fresh and the pickles agreeably sour, but the fries were soggy, to my dismay and The Niece's delight. The 4 of us split 3 slices of pie at the end of the meal - Apple, Chocolate Cream and Maple Walnut. The verdict: The apple wasn't as good as the LSW's, but the Maple Walnut and Chocolate Cream were worth the trip.
The LSW will be reporting on the handmade chocolates she tracked down in Walpole, NH here. Ye gods, they are good! And then there was 'Smokin' Bowls' on 123 between Bellows Falls and Chester:

Does this look good or what? We ordered the 'Brownie of the day'; tasty but - unfortunately - strictly legal.
Now, down to business:
As I noted, the reason for the trip was to get land clearing, excavating, and foundation estimates. To that end, I spent all of Friday afternoon and part of Saturday morning on site, taking time to walk the property and clearing some of the underbrush between appointments. The weather was in the mid-50's and the sun shining, and I spent most of the day in a T-shirt. Nice.
I started by locating the engineer's markers, which was a little challenging as a fallen pine took out the well marker. Once I found it, I was able to triangulate the planned position of the cabin and mark it with orange poles. The slope of the land seemed to lend itself to a walk-out basement, and before I knew it I was getting estimates on one at 28 x 32 in addition to my less ambitious 16 x 28 crawl space.
I talked with 6 contractors in total. Some things I learned:
- When the land it cleared the excavator will expect to take away any salvageable wood. If you choose to keep it, the cost of the work will go up.
- The cost of land-clearing will go down if the stumps can be buried on the property. Brush will be burned if weather conditions permit, or chipped if not.
- Excavation will include digging the holes for the footings, leveling and prepping the floor for the rat slab, laying the drainage pipe, and back-filling and grading when the work is done.
- The excavator can also be expected to rough-in the septic pipe and a 4" PVC conduit for the well. He/She should also run both pipes 10' beyond the foundation to make sure you're not trying to dig into the stone that will be laid down over the drainage pipes.
- Well-drilling rigs require a roughly level surface and wide access to the well site.
- The driveway should only be roughed-in until the foundation is done. After that, it should be at least sub-surfaced until all of the work on the site is finished.
- Excavation and Land-Clearing estimates can vary significantly. Mine ran from a low of $4,000 to a high of $9,000.
- Pouring the foundation will need to wait until at least mid-May, when the prohibition against heavy trucks on most unpaved roads during 'mud season' is lifted.
- It will take 3 days to pour the foundation, and about a week for it to cure. Once it is in, the building needs to go up before winter to protect it.
- Foundation estimates seem to vary less than excavating. For a 16 x 28 frost-wall foundation including a rat slab, I'm apparently looking at between $5,000 - 6,000.
The 'official' estimates are all expected before the end of this week, so I anticipate we'll be underway within a month. The first step will be land clearing, which is expected to take about 2-days, as most of the trees on the site are relatively small.
Here's a shot of the building site:

The view behind the future cabin:

In this shot the two large boulders mark the future driveway:

Incidentally, the major lesson learned on this trip was that a Hyundai Sonata is not the best vehicle with which to sample dirt-surfaced mountain passes during mud season. I see a Subaru in the LSW's future...