I read somewhere that when you have a lockable shell, you're only about 40 done. That seems slightly pessimistic when I quickly tick off the remaining items, but clearly realistic when I sit down to write out what still needs to be done in detail. Add in the amount of time it actually takes to cross any given item off the list, and you begin to wonder if you'll ever actually be finished.
But "the journey of a thousand miles begins with a single step", and so each weekend I plod along, a bit overwhelmed but still enjoying the journey. Since the last post, there have been 3 trips to Shangri-La, two solo and one with LSW and The Boy in tow.
On the first trip I arrived with a punch list of items: Finish siding the south wall, build the bridge between the lofts, and put up the walls in the crawlspace. A solid day's work, I figured forgetting that a day is 24 hours at best, and only 8 hours realistically given the 6 hours of travel. In the end, the siding was all I accomplished, and even that I ran out of before the south wall was done.
No worries, though - we had planned an overnight the following weekend, and we had big plans to make bigger progress. We were up early and out on time for once, the wife actually stayed awake the whole trip and companionable banter sped the journey along. The Boy was in a good mood, the sun was shining and the mercury settled in the low 70s. Everything was absolutely perfect until we pulled up in front of the cabin and I turned off the car.
"Tell me you brought the keys," I said to the LSW.
"I thought you had them," she replied.
Son of a ...
Faced with a challenge from the universe to practice my zen actively, I calmly dropped the family at our beloved Saxtons River Inn, and spent the next 6 hours in a round-trip journey to retrieve the keys.
Here's the thing, though: Compelled to book a second night, we were pleased to be given the best room in the place "because we were regulars". Sitting that second night with a cold beer after a long day of work on our private front porch overlooking the main street, I had one of those moments where everything - and I mean everything - felt perfect and I knew life could not possibly be any better. So there was that, anyway.
And what did we get done? The deck framing is in place for the front porch, the rear gable is ready for the power hookup and both the general and oven circuits have been run. Less work than I thought we could accomplish, but what else is new?
This last weekend I was on the road by 5:30 am and hard at work by 8:45. I would have been there a little sooner, but I couldn't resist stopping at the Saxtons River Market for a bottled water and a hot donut. Those donuts will kill me one day, but what a way to go. The weather was deceptive: It was the kind of day where you felt slightly chilled while standing still, but were pouring rivers of sweat as soon as you lifted any tool. Really, really, really, humid. I didn't do too bad, though: The walls are up in the crawlspace and the bridge is finally built between the lofts. I rewarded myself with a hot roast beef and Cheddar from the Putney Co-op and listened to the dishy 'Mrs. Astor Regrets' on CD on the way home. The latter is a guilty pleasure, but then who doesn't like to hear about the self-destruction of the rich?
Unless of course, you're the rich in question. Then it just sucks.
In other news, Larry expects to get the meter socket on the house this week, and he'll be contacting me soon about running the power to the panel and hooking up the first couple of circuits. I understand that the revised septic plans are on their way to the State of VT as of last Friday, and even as I write I'm waiting for a callback from Green Mountain Well Drilling about moving my well date from the end of July to the end of June. All good stuff.
A middle-aged corporate everyman struggles to realize his dreams of a place in the country
Shangri La
Showing posts with label Saxtons River Market. Show all posts
Showing posts with label Saxtons River Market. Show all posts
Monday, June 7, 2010
Saturday, October 24, 2009
The Slow Work

I have read that the framing is the fastest (and most gratifying) part of building a house - it's all rough cuts and rough nailing, and every day you see big progress as a wall goes up or a roof goes on. And it's true - each weekend this summer left a feeling of accomplishment in its wake, each new picture on my desktop at work drawing comments from passers-by, astonished that one of their desk-jockey compatriots could successfully assault a task so seemingly daunting.
Now? Not so much. The picture from 3 weeks ago showed siding on one side of the building up to the first window. 2 weeks ago the picture had siding up to the 2nd window. With any luck, this week's picture will show one side finished. My co-workers are starting to sneak past my desk without comment.
In fairness to me, I'm now working by myself, one day a week, in increasingly cold weather. By the time I get there and set up, it's almost 10, and I begin to pack up for home by 2. Not exactly a recipe for rapid progress. But the goal is to get all the trim up and get one wall sided, so I keep plugging away. (Thank god, by the way, that I chose white pine shiplap rather than shingles; at this rate I'd be 3 years dead of old age before the shingles would be finished.)
I expect that this weekend (or next) will be the last for the year, and then we'll settle for staying at the Saxton's River Inn once per month (they gave us the corporate rate - thanks!) to check on the place and have a nice meal. Maybe we'll spend some time getting better acquainted with the other 2.5 acres on the property, and I've promised The Boy we'd do some sledding - the cleared slope of land from the cabin to the utility right-of-way should be perfect for it. Might even rent a snow machine or two and explore some of the VAST trails. In any event, it will be nice to go up to relax for a few weekends for a change.
On the plus side, our little slice of heaven has been painfully picturesque as the fall has progressed, and the fresh donuts at the Saxton's River Market seem to get even better as the temperature drops. With the leaves gone, I've noted that - with a little clearing - we've got an potentially nice view of the ridge to the West to add to the current view from the East. We'll have the perfect view from either porch. Nice.